Qiancheng Group Lao Center: Home Letter - October Construction Progress Update

Source: Published:2025-11-13 18:00:43 Views: 192

Time holds the pen, craftsmanship forges the "home" scene.

From the blueprints on paper, to the reality soon to unfold,

Making the warmth of home within easy reach.

Filled with beauty and sincere intentions,

This warm family letter arrives as scheduled,

Inviting you to witness the beauty of your future home together.

「 October Construction Progress Update」

I. Annex Building Progress

1. Main Structure & Secondary Works: The main structure of the annex building was fully completed in May, and the secondary structural work has now been 100% finished.

1.jpeg

2. Garage Finishing: The garage floor pouring has been 100% completed, the carborundum grinding has been 100% finished, and the painting of walls and ceilings is 90% completed.

2.jpeg
3.jpeg
4.jpeg
5.jpeg
6.jpeg

3. Facade Works: The external wall plastering of the annex building has been 100% complete; the external wall painting is 60% finished; the installation of door and window frames, railing columns, and aluminum plate keels has reached 95% completion; and the installation of external window glass is 90% completed.

7.jpeg
8.jpeg
9.jpeg
10.jpeg
11.jpeg
12.jpeg
13.jpeg
14.jpeg

4. Mechanical & Electrical Installation: The installation of concealed water and electricity works as well as rainwater and sewage pipelines has been 100% completed;the air conditioning commissioning for Floors 8-12 of the annex building has been finished; the elevators have been fully commissioned and put into use, the installation of lighting fixtures on Floors 8-12 is 100% completed; and the overall installation of cable trays on Floors 1-5 has been 100% finished.

15.jpeg

5. Interior Finishing: The construction of light-weight partition walls and concealed works has been 100% completed; the ceiling cladding is 100% finished; the putty application for walls and ceilings has reached 95% completion; the overall tiling of wall and floor tiles is 95% completed; the installation of wood veneers and woodwork is 80% finished; hard finishing, detailed touch-ups and cleaning works are being carried out floor by floor; soft furnishings have been delivered to the site, with 60% of the carpet laying completed, and the overall installation of cabinets, office desks and chairs, curtains, bedroom linens and other items is 40% finished.

16.jpeg
17.jpeg
18.jpeg
19.jpeg
20.jpeg
21.jpeg
22.jpeg
23.jpeg
24.jpeg
25.jpeg
26.jpeg
27.jpeg
28.jpeg
29.jpeg
30.jpeg
31.jpeg
32.jpeg
47.jpeg
34.jpeg
48.jpeg


II. Main Tower Progress

Main Tower: The pouring of the fourth-floor base slab for the main structure of Zone A has been completed; for Zone B, the erection of internal scaffolding and formwork for the first floor of the main structure is finished, with formwork construction in progress; for Zone C, the construction of the foundation bed course and waterproofing works has been 100% completed, and the steel bar binding for the raft slab has reached 30% completion.

35.jpeg
36.jpeg
37.jpeg
38.jpeg
39.jpeg
40.jpeg
41.jpeg
42.jpeg

III. Aerial Actual Scenery of the Project

43.jpeg
44.jpeg
45.jpeg
46.jpeg


图片关键词
图片关键词
图片关键词
图片关键词


图片关键词

Every brick and tile, every line of words,

Embodies the essence of the craftsman spirit.

We pay close attention to the living needs of property owners,

All to bring you the beautiful life you envision.